All case studies Case study · 01

30% of orders late. Then 8%.

A 120-person metal fabricator in Hamilton, Ontario.

IndustryMetal fabrication
LocationHamilton, ON
Headcount120

The situation

The schedule was in one foreman's head, and about 30% of orders were shipping late.

What we did

We built a visual schedule board and ran a weekly planning meeting.

What changed

30% → Under 8% Orders shipping late

Late orders came in under 8% in four months.

Marcus didn't bring software. He brought a whiteboard and a meeting, and it's still running two years later.
The owner, Hamilton